Browse all questions
Every question with its answer and explanation — study by topic or all at once.
Contracts & Execution
336 questionsCalifornia requires a written home improvement contract for any work on a residential property totaling $500 or more, including both labor and materials (B&P §7159). Note: this $500 written-contract threshold is a DIFFERENT number from the $1,000 unlicensed minor-work threshold under §7048 — SB 517 amended §7159 for 2026 (subcontractor-disclosure rules), but left this $500 figure in place, so do not confuse the two.
Bus. & Prof. Code §7159The three-day right of rescission applies to contracts solicited and signed at the consumer's home. The homeowner has until midnight of the third business day to cancel without penalty.
Bus. & Prof. Code §7159(b)California law requires home improvement contracts to include the contractor's name, address, license number and expiration date, description of work, project start and completion dates, and payment schedule.
Bus. & Prof. Code §7159All changes to a home improvement contract must be documented in a written change order signed by both the contractor and homeowner before the changed work begins.
Bus. & Prof. Code §7159(d)A contractor may not demand or accept final payment until the project is substantially complete. Demanding payment before this point is a violation of California Contractors' Law.
Bus. & Prof. Code §7159Arbitration clauses are permitted in construction contracts but must be clearly disclosed, written in at least 10-point boldface type in home improvement contracts, and separately initialed by the homeowner.
Bus. & Prof. Code §7191Abandonment without legal excuse exposes a contractor to license discipline (suspension/revocation), civil liability for breach of contract, and potentially criminal charges for misappropriation of funds.
Bus. & Prof. Code §7107While permits can technically be pulled by the owner, it is the contractor's professional responsibility to ensure all required permits are obtained before work begins. Working without required permits is a license violation.
Bus. & Prof. Code §7090A force majeure clause excuses a party from performance when extraordinary events beyond their control (weather, acts of God, pandemics) prevent timely completion. It protects the contractor from delay damages.
Liquidated damages are enforceable if: (1) damages were difficult to estimate at contract signing, and (2) the amount is a reasonable estimate of probable harm — not a penalty.
Civil Code §1671The preliminary notice is not a demand for payment — it preserves the right to file a mechanics' lien later if the contractor or supplier is not paid. Without it, lien rights may be lost.
Civil Code §8200A T&M contract pays the contractor for actual labor hours at an agreed rate plus actual material costs, typically plus overhead and profit markup. The total cost is not fixed in advance.
Under a fixed-price (lump sum) contract, the contractor agrees to complete the work for a set price regardless of actual costs. If costs exceed the estimate, the contractor absorbs the loss.
The prime contractor can withhold payment from the defaulting subcontractor, hire a replacement to complete the work, and sue the original sub for any additional cost incurred above the original subcontract price.
On private works, owners must pay general contractors within 30 days of a proper undisputed invoice. On public works the period is 30 days from invoice or 39 days from billing, depending on the agency.
Civil Code §8800Because payment comes from the owner, this is a private project. Under Civil Code §8814 (and B&P §7108.5), a direct (general) contractor must pay each subcontractor its share within 7 days of receiving a progress payment from the owner, or face a 2%-per-month penalty. Ten days is the separate deadline for releasing withheld retention to a subcontractor — not the progress-payment rule this question asks about.
Civil Code §8814California's Right to Repair Act (SB 800) establishes statutory warranties for new residential construction: 1 year for most components, 4 years for plumbing/electrical/mechanical, 10 years for structural defects.
Civil Code §896California limits the down payment on a home improvement contract to $1,000 or 10% of the contract price, whichever is LESS. Here 10% would be $4,000, so the smaller cap of $1,000 controls.
Bus. & Prof. Code §7159.5The down payment may not exceed $1,000 or 10% of the contract price, whichever is less. Ten percent of $6,000 is $600, which is less than $1,000, so $600 is the legal maximum.
Bus. & Prof. Code §7159.5Home improvement contracts must state the work description, payment schedule, and start/completion dates, among other items. A homeowner's income is private financial information and is never a required contract term.
Bus. & Prof. Code §7159The contractor must furnish the buyer a fully completed and signed copy of the home improvement contract before any work begins, so the buyer can review terms and exercise cancellation rights.
Bus. & Prof. Code §7159A buyer may cancel a home solicitation home improvement contract until midnight of the third business day after signing. The cancellation right is exercised by written notice delivered within that window.
Bus. & Prof. Code §7165California prohibits front-loading. Each progress payment must not exceed the value of work actually performed and materials actually delivered, protecting the homeowner if the contractor stops work.
Bus. & Prof. Code §7159.5An arbitration clause in a contract for residential work must appear in at least 10-point boldface type, contain prescribed disclosure language, and be separately initialed or signed by the consumer.
Bus. & Prof. Code §7191Any change in the contract price, scope, or terms must be documented in a written change order signed by both parties. Verbal change orders are unenforceable and a license law violation.
Bus. & Prof. Code §7159B&P Code §7164 sets the required terms for contracts to build a new single-family residential structure sold to the person it is built for. Home improvement (remodel/repair) contracts are governed by §7159.
Bus. & Prof. Code §7164The law requires the contract to bear a clear heading identifying it as a "Home Improvement" contract so the consumer knows which set of protective rules applies to the agreement.
Bus. & Prof. Code §7159A person who solicits or negotiates home improvement contracts on behalf of a contractor must be registered with the CSLB as a Home Improvement Salesperson (HIS), unless they are an officer of the licensed entity.
Bus. & Prof. Code §7159The contract must contain a notice describing the CSLB, including its contact information, so consumers know how to verify a license, learn about the contractor's history, and file a complaint.
Bus. & Prof. Code §7159The contractor must attach to the contract a properly completed Notice of Cancellation (typically two copies) that the buyer can complete and mail to exercise the three-day cancellation right.
Civil Code §1689.7While the standard home solicitation cancellation period is three business days, California extends the cancellation period to seven business days for senior citizens, including certain disaster and emergency repair contracts.
Civil Code §1689.6Upon a valid cancellation, the seller must, within 10 days, refund all payments made and return any goods traded in. The contractor may not retain a fee for a properly cancelled contract.
Civil Code §1689.7Any home improvement work over $500 requires a written contract before work begins. Starting on a verbal agreement violates license law and exposes the contractor to discipline and unenforceable payment claims.
Bus. & Prof. Code §7159It is unlawful to demand or accept a payment that exceeds the value of the work performed and materials delivered. The other choices describe proper, lawful contracting practices.
Bus. & Prof. Code §7159.5Willfully departing from or disregarding plans or stopping work without legal excuse and without the owner's consent is abandonment, a cause for license discipline under B&P §7107.
Bus. & Prof. Code §7107A fixed-price or lump-sum contract sets one total price for the entire scope. The contractor profits if costs come in low and loses if they run high, bearing the cost risk.
In a cost-plus-percentage contract, the contractor is reimbursed for actual costs and earns a fee equal to an agreed percentage of those costs. The owner bears most of the cost risk.
A unit-price contract sets a price per unit of work (per cubic yard, per linear foot, etc.). The total contract value depends on the actual measured quantities completed.
In a GMP contract, costs are reimbursed up to a negotiated ceiling. Any cost overrun above the cap is borne by the contractor, capping the owner's financial exposure.
Margin is gross profit divided by the selling price. Profit is $100,000 - $80,000 = $20,000; $20,000 / $100,000 = 20% margin. (Markup, by contrast, divides profit by cost: $20,000 / $80,000 = 25%.)
Showing 40 of 336
Last reviewed: · editorial process
What's on the California CSLB Business & Law Exam?
The California CSLB Business & Law Exam is administered by the California Contractors State License Board (CSLB). Topic weights below come directly from the official exam blueprint — focus your study on the highest-weighted areas first.
Official source: California Contractors State License Board (CSLB) →
Topic blueprint
- 21%Contracts & Execution
- 20%Employment
- 15%Business Finances
- 14%Safety
- 13%Business & Licensing
- 12%Insurance & Liens
- 5%Public Works
How hard is the exam?
Moderate difficulty. The CSLB Business & Law exam (115 questions, 3.5 hours, ~73% to pass) is dense with contract law, payroll rules, and Cal/OSHA safety standards. Most candidates pass on the first or second attempt with focused study.
- Recommended study hours
- 40-80 hours over 4-8 weeks (most candidates)
- First-attempt pass rate
- Approximately 60-65% first-attempt pass rate (industry estimate; CSLB does not publish official rates). Repeat-takers typically pass within 2-3 attempts.
- Where to focus first
- Contracts (largest topic by exam weight) and Cal/OSHA Safety — together these are usually 40%+ of the exam.
Figures (pass rates, fees, salaries) are approximate and can change — always verify with the official testing body or licensing board before you rely on them.
Frequently asked questions
How many CSLB Business & Law practice questions are in this bank?+
1,605 original practice questions across all 7 topics of the CSLB Business & Law exam, with full explanations and California statute citations on every question.
Is the CSLB Business & Law practice free?+
Yes — every practice question, organized by topic with full explanations, is free and needs no signup. The full timed mock exam (mock-readiness score, PDF report and weak-area retest) is free too. The only paid product is our optional $9.99 study-guide eBook.
Are these the real CSLB exam questions?+
No. All questions are 100% original prose authored from public-domain sources (California Business and Professions Code, Civil Code, Labor Code, Title 16 CCR). We never copy from real CSLB exams or paid prep providers.
What topics does the CSLB Business & Law exam cover?+
Seven topics: Business Organization & Licensing, Business Finance, Employment Requirements, Insurance & Liens, Contracts & Performance, Public Works, and Safety.
What's the passing score for the CSLB Business & Law exam?+
A pass mark of about 73% is commonly cited by exam-prep providers, but CSLB does not publish a fixed public raw-score cutoff — it reports only PASS/FAIL. The real exam is 115 questions over 3.5 hours at a PSI testing center; a solid practice target is 75%+.
Can I take the CSLB exam in Spanish?+
Yes — the official CSLB exam is offered in English and Spanish. Other languages may be available by translator request (4–6 weeks lead time). PrepPass practice questions are available in English, 中文, and Español.
Does PrepPass track which questions I get wrong?+
Yes — sign up free and the 'My mistakes' filter shows you only the questions you've missed across all your practice sessions. It updates automatically as you re-attempt and get them right.