Operational Procedures第 77 / 100 题
According to standard change management, what must typically happen before a significant change is implemented in a production environment?
a.Nothing; changes are made immediately
b.Only the technician's verbal note
c.A social media post
d.Documented request, risk analysis, and approval by the change board
解析
Significant changes generally require a documented request, risk assessment, and formal approval before implementation to control impact. Making changes without review or approval undermines stability and accountability.
免费刷完整 100 道题库 — 无需注册。
同考点相关题目
- Why is it important to maintain accurate, up-to-date documentation such as network diagrams and asset inventories?
- In a formal change-management process, what should be prepared in case a change causes unexpected problems in production?
- Which safety practice protects sensitive electronic components from static discharge while a technician works inside a computer?
- Which document defines the acceptable ways employees may use company computers, networks, and internet access?
- When handling a customer's confidential data during a repair, which behavior best respects privacy and professional conduct?
- Which fire extinguisher class is appropriate for electrical fires involving energized equipment?