Hardscape & Grading第 61 / 100 题
Compaction of subgrade soil before hardscape is measured against what standard reference?
a.The color of the soil
b.The soil's pH
c.The number of passes only
d.A percentage of maximum dry density (for example, 90 to 95 percent)
解析
Compaction is specified as a percentage of a soil's maximum dry density determined by a laboratory Proctor test, commonly 90 to 95 percent for hardscape subgrade. Field testing verifies the soil reaches the required density. Adequate compaction prevents future settlement under pavement.
免费刷完整 100 道题库 — 无需注册。
同考点相关题目
- A paved surface should be sloped for drainage at about what minimum cross slope?
- A catch basin connected to underground drain pipe is used to do what?
- When laying out a site from a plan, a builder's level or laser level is used primarily to establish what?
- On expansive clay soils, hardscape and foundations are at risk because the soil does what?
- A dry-stack (mortarless) segmental block wall relies on what for stability?
- Directing a downspout's discharge onto a splash block or into a pipe that carries it away from the house prevents what?