Planning & Estimating第 80 / 100 题
When would a contractor typically need to obtain a permit related to painting work?
a.For any interior repaint of a single room
b.Permits are never required for construction work
c.When the work is part of larger construction requiring permits, or involves regulated activities like certain lead abatement
d.Only when using latex paint
解析
Routine repainting usually does not need a building permit, but painting tied to larger permitted construction, or regulated activities such as lead abatement, may require permits or certifications. Contractors verify local requirements before starting. Lead work in pre-1978 housing also carries federal RRP obligations.
免费刷完整 100 道题库 — 无需注册。
同考点相关题目
- To estimate labor, a painter uses a production rate. If one painter coats 150 sq ft per hour and the job is 1,200 sq ft for one coat, how many labor-hours are needed?
- Why should surface prep be estimated as a separate labor item?
- A ceiling measures 20 ft by 15 ft. How much area must be covered?
- A job requires 18 gallons of paint at $45 per gallon. What is the material cost for the paint?
- Why do estimators add a factor for waste and touch-up when calculating paint quantities?
- A wall is 50 ft long and 8 ft high with one 3 ft by 7 ft door opening. Using an area takeoff that deducts the door, what is the net paintable area?