安全第 1299 / 1605 题
Before renovation or demolition of an older building, the standard approach to potential asbestos-containing materials (ACM) is to:
a.Presume certain materials are ACM unless proven otherwise, and have them surveyed/tested by qualified personnel
b.Wet the material and grind it up
c.Assume none is present and proceed
d.Let any worker remove it
解析
1926.1101 presumes certain materials (e.g., thermal system insulation, surfacing material in pre-1981 buildings) contain asbestos unless a survey/testing shows otherwise. Disturbing ACM without controls exposes workers to a carcinogen.
法律依据: 29 CFR 1926.1101免费刷完整 1605 道题库 — 无需注册。
同考点相关题目
- OSHA's respirable crystalline silica standard for construction includes 'Table 1,' which:
- The permissible exposure limit (PEL) for respirable crystalline silica under the OSHA construction standard is:
- Under the silica standard, employers must also establish and implement a:
- The permissible exposure limit for asbestos is 0.1 fiber per cubic centimeter as an 8-hour TWA. Work disturbing asbestos is organized into:
- Which is a required control when performing higher-risk (Class I) asbestos removal?
- When workers may be exposed to lead during construction (e.g., disturbing lead-based paint), the employer must initially: