Codes & Safety第 109 / 120 题
A water distribution system that will operate at 45 psi working pressure is tested with water. The plumber pumps it to 48 psi, and after 15 minutes the gauge reads 46 psi. How should the result be reported?
a.Pass, because the test pressure of 48 psi exceeded the 45 psi working pressure of the system
b.Fail, because the test must be at the working pressure but not less than 50 psi and must hold for 15 minutes with no drop
c.Pass, because a 2 psi drop over 15 minutes is within the allowable tolerance for a supply test
d.Fail, because a water supply system may only be tested with compressed air at 100 psi
解析
The supply test is run at the system's working pressure but never less than 50 psi, and it must hold for at least 15 minutes without a loss of pressure, so a 48 psi start that falls to 46 psi fails on both counts. Exceeding the working pressure alone is not enough when the code sets a 50 psi floor. There is no allowable pressure drop; any drop indicates a leak. Air may be permitted as an alternate test medium in some jurisdictions, but it is not the only method and 100 psi is not the required value.
法律依据: IPC §312.5免费刷完整 120 道题库 — 无需注册。
同考点相关题目
- A drainage, waste and vent system is being water tested. Which statement describes the test correctly?
- A high-rise DWV system is water tested in sections. The highest joint in the section currently under test is 28 ft above the building drain, and three more floors of piping continue above that section. To what height above the building drain must the test standpipe extend?
- Freezing weather makes a water test impractical, so the DWV rough-in is air tested instead. Which combination of test pressure and duration satisfies the code?
- On a set of plumbing drawings, which view shows the vertical arrangement of the DWV piping, the floor-to-floor relationships and the order of the connections, drawn at an angle and generally not to scale?
- A floor plan is drawn at a scale of 1/4 in = 1 ft. A straight run of cold water piping measures 3-1/2 in on the drawing. What is the actual length of that run?
- A site plan shows the invert elevation of a building sewer as 102.50 ft at the upstream end and 101.90 ft at the downstream end, with 48 ft of run between the two points. What is the slope of the sewer in inches per foot?