Code Admin & Safety第 106 / 110 题
During electrical construction, a rough-in (rough) inspection is generally performed:
a.After energizing the system
b.Before wiring is concealed or covered
c.Only at final occupancy
d.After the final inspection
解析
The rough inspection occurs after wiring is installed but before walls or wiring are covered, so the inspector can verify concealed work.