Administration第 76 / 110 题
A jurisdiction charges a plumbing permit fee of a $75 base plus $12 per fixture. A project has 18 fixtures. What is the permit fee?
a.$216
b.$249
c.$366
d.$291
解析
Fee = base + (per-fixture x count) = 75 + (12 x 18) = 75 + 216 = $291. Fixture-based fee schedules tie the permit cost to the scope of work, so an accurate fixture count is needed both for the fee and for sizing. Forgetting the base fee gives the too-low $216.
法律依据: UPC §103.0免费刷完整 110 道题库 — 无需注册。
同考点相关题目
- During construction the plumbing is inspected in stages. Which sequence correctly orders the common inspections?
- A DWV rough-in is water tested. The test fills the system with water to create a 10 ft head at the lowest point. Using 0.433 psi per foot, what pressure does a 10 ft water column exert at the base, and what does the test prove?
- On an isometric, a 45-degree offset must clear an obstruction, producing a 24 in vertical offset. For a 45-degree fitting the travel (diagonal) length equals the offset times 1.414. What is the travel length of pipe between the two fittings?
- A plumbing job has a direct cost of $9,000. The contractor wants a 20 percent profit margin measured on the selling price (not markup on cost). Using price = cost / (1 - margin), what is the selling price?
- A master plumber estimates a job. A takeoff lists 260 ft of 3/4 in copper, 40 ft of 1 in copper, and 18 fittings. What is the estimator computing at this stage?
- A plumbing contractor prices a job using material of $4,200 and labor of $6,000, then adds 15 percent overhead and 10 percent profit on the combined cost. What is the approximate bid price?