Operational Procedures第 92 / 100 题

Under change management, why should a change include a documented 'end-user acceptance' or verification step after implementation?

a.To increase RAM automatically
b.To disable logging
c.To confirm the change works as intended and the issue is resolved
d.To overclock the GPU

解析

Verifying end-user acceptance confirms the change achieved its goal and did not introduce new problems before the change is closed. It does not alter hardware or logging by itself.