合同与履行第 790 / 1605 题

Taken together, the home improvement contract rules of §7159 require all of the following EXCEPT:

a.A down payment no greater than $1,000 or 10%, whichever is less
b.A written contract when the price exceeds $500
c.Full prepayment of the contract price before any work begins
d.A schedule of payments tied to work performed and mandatory consumer notices

解析

Full prepayment before work begins is exactly what §7159 forbids; the statute limits down payments and ties progress payments to work performed while requiring the written contract and notices.

法律依据: B&P §7159

免费刷完整 1605 道题库 — 无需注册。

同考点相关题目

最近核对: · 审核流程

Sen Lin, PrepPass 创始人 · 依据官方资料核对 California CSLB Contractor License Law & Business Exam · 我们如何核对
审核人 Abraham Chen Licensed California General Contractor (CSLB License #1101856 核实)