Which best describes when the contract price and payment terms must be filled in on a home improvement contract?

a.Before the buyer signs, so no material terms are blank
b.Only if the buyer asks for figures
c.After the first inspection
d.Any time within a week after signing

解析

All material terms, including price and payment schedule, must be completed before the buyer signs; having the buyer sign a contract with blanks to be filled in later is a prohibited practice.

法律依据: B&P §7159