合同与履行第 813 / 1605 题
During a remodel, the owner asks the contractor to add a skylight not in the original plans. The BEST practice before performing this extra work is to:
a.Verbally agree and rely on memory
b.Refuse because contracts can never be modified
c.Prepare and have both parties sign a written change order describing the added scope and price before proceeding
d.Do the work first and add it to the final invoice as a surprise
解析
Best practice is to document any added or changed work with a signed written change order stating the new scope and price before performing it. This protects the contractor's right to payment and gives the owner clarity on cost. Performing extras without written authorization risks nonpayment disputes and, for many contracts, may violate license-law requirements that changes be in writing. Contracts can be modified; the key is doing so clearly and in writing.
免费刷完整 1605 道题库 — 无需注册。
同考点相关题目
- Specific performance, a remedy that compels a party to actually perform the contract, is most commonly granted in disputes involving:
- Rescission as a contract remedy means:
- A written change order in construction is best described as:
- A contractor performs extra work at the owner's oral request but has no written change order. When the owner refuses to pay, the contractor's recovery may still be possible under which theory?
- Which statement about oral change orders on a construction project is most accurate?
- An express warranty in a construction contract is: