合同与履行第 825 / 1605 题

A liquidated damages clause in a construction contract is best described as:

a.A penalty designed to punish the contractor
b.A pre-agreed reasonable estimate of damages payable if a specified breach (often late completion) occurs
c.A clause that liquidates (sells off) the contractor's assets
d.A clause forbidding any damages at all

解析

A liquidated damages clause fixes, in advance, a reasonable estimate of the damages one party will owe if a specified breach occurs, most commonly a set dollar amount per day of late completion. It is enforceable when actual damages would be difficult to calculate and the amount is a reasonable forecast, not a penalty. Courts refuse to enforce clauses that are actually penalties, and the clause is unrelated to liquidating assets or barring damages.

免费刷完整 1605 道题库 — 无需注册。

同考点相关题目

最近核对: · 审核流程

Sen Lin, PrepPass 创始人 · 依据官方资料核对 California CSLB Contractor License Law & Business Exam · 我们如何核对
审核人 Abraham Chen Licensed California General Contractor (CSLB License #1101856 核实)
反馈