合同与履行第 836 / 1605 题
A general contractor delegates the plumbing work to a licensed plumbing subcontractor. With respect to the owner, the general contractor generally remains:
a.Liable only if the subcontractor is unlicensed
b.Responsible to the owner for the subcontractor's performance under the prime contract
c.Unable to be paid for any of the work
d.Completely relieved of all responsibility for the plumbing
解析
Delegating performance to a subcontractor does not, by itself, relieve the general contractor of its obligations to the owner. The prime contractor remains responsible to the owner for the entire scope, including the subcontracted plumbing, unless the owner agrees to a novation releasing the general. The general's continuing responsibility is independent of whether the sub is licensed, and delegation does not forfeit the general's right to payment for completed work.
免费刷完整 1605 道题库 — 无需注册。
同考点相关题目
- A construction contract contains a valid clause requiring the parties to arbitrate all disputes. If one party nonetheless files a lawsuit in court, the other party can typically:
- One commonly cited advantage of arbitration over traditional litigation is that it:
- Assignment of a contract generally refers to:
- Which type of contractual duty is generally NOT delegable to another party without the other party's consent?
- A 'novation' occurs when:
- A written subcontract requires the general contractor's prior written approval before the subcontractor may assign the subcontract. The subcontractor assigns it anyway with no approval. The assignment is most likely: