If a contractor's overhead is fixed at $10,000 per month and he completes 5 jobs that month, the average overhead absorbed per job is:
a.$1,000
b.$5,000
c.$50,000
d.$2,000
解析
Average overhead per job = total monthly overhead / number of jobs = $10,000 / 5 = $2,000. Completing more jobs spreads fixed overhead over more work, lowering the per-job burden.
免费刷完整 1605 道题库 — 无需注册。
同考点相关题目
- A contractor sells a job for $60,000 that cost $45,000. What is the gross profit margin?
- A contractor's annual overhead is $75,000 and projected direct costs are $500,000. On a job with $20,000 direct cost, how much overhead should be allocated using the cost-based method?
- A contractor bids a job with $15,000 direct cost, adds 18% overhead, then 12% profit on the subtotal. What is the total bid (rounded to the nearest dollar)?
- On a balance sheet, which of the following is a CURRENT asset?
- On a balance sheet, which is a CURRENT liability?
- A contractor's net profit is $48,000 on revenue of $600,000. What is the net profit margin?