Codes & Safety第 104 / 120 题
Underground drainage piping is installed, and the crew backfills and compacts the trench before the groundwork inspection is called for. What does the code require?
a.The work is accepted if the plumber photographed the piping and the joints before backfilling
b.The inspector may simply carry the groundwork over and approve it at the rough-in inspection
c.A reinspection fee is paid and the buried piping is accepted as installed
d.The concealed work must be uncovered and exposed for inspection, and the cost of uncovering and restoring it is borne by the permit holder
解析
Inspections follow a set sequence, typically groundwork or underground, then rough-in or top-out, then final, and no portion of the work may be covered or concealed until it has been inspected and approved. When work is covered early, the code allows the inspector to require it to be uncovered at the permit holder's expense. Photographs are not a substitute for the inspector's own examination and pressure test. Paying a reinspection fee covers the inspector's return trip; it does not buy approval of work no one has seen.
法律依据: IPC §107免费刷完整 120 道题库 — 无需注册。
同考点相关题目
- A homeowner hires a plumbing company to replace a water heater and reroute the gas line to it. A journeyman employed by that company will perform the installation. Under a typical adopted plumbing code, who is authorized to apply for and hold the permit?
- Model plumbing codes are published on a three-year cycle. A state adopts one of those editions with statewide amendments, and a city then adopts the state code with additional local amendments. Which document governs an installation in that city?
- A drainage, waste and vent system is being water tested. Which statement describes the test correctly?
- A high-rise DWV system is water tested in sections. The highest joint in the section currently under test is 28 ft above the building drain, and three more floors of piping continue above that section. To what height above the building drain must the test standpipe extend?
- Freezing weather makes a water test impractical, so the DWV rough-in is air tested instead. Which combination of test pressure and duration satisfies the code?
- A water distribution system that will operate at 45 psi working pressure is tested with water. The plumber pumps it to 48 psi, and after 15 minutes the gauge reads 46 psi. How should the result be reported?