A master plumber must schedule labor. A job is estimated at 240 labor-hours and the crew provides 3 plumbers working 8-hour days. How many working days are needed?

a.8 days
b.10 days
c.12 days
d.15 days

解析

Crew capacity per day = 3 plumbers x 8 hours = 24 labor-hours, so days = 240 / 24 = 10 working days. Estimating duration from labor-hours and crew size lets the contractor commit to a realistic schedule. Underestimating crew hours leads to missed completion dates and penalties.

法律依据: UPC §103.0