A contractor prepares an estimate and adds 15% to cover overhead and 10% profit on top of that. If direct costs are $50,000, what is the bid price?
a.$57,500
b.$62,500
c.$63,250
d.$65,000
Explanation
$50,000 × 1.15 (overhead) = $57,500; $57,500 × 1.10 (profit) = $63,250. Overhead is applied first to the cost, then profit is applied to the overhead-loaded cost.
Practice all 690 questions free — no signup required.
Related questions on this topic
- A contractor's job cost sheet shows: Materials $30,000, Labor $20,000, Subcontractors $15,000, Overhead allocation $10,000. What is the total direct job cost?
- A contractor takes out a $50,000 equipment loan at 8% annual interest. What is the simple interest owed for 6 months?
- Cash flow problems in contracting most commonly occur when:
- Which financial statement shows a contractor's assets, liabilities, and equity at a specific point in time?
- A contractor's accounts receivable are growing while cash on hand is shrinking. This most likely indicates:
- Which type of insurance protects a contractor if a third party is injured on the job site?
Last reviewed: · editorial process
PrepPass Editorial Team · Verified against California CSLB Contractor License Law & Business Exam · How we review