An owner wants to remove a $60,000 mechanics' lien recorded against the property so the property can be sold or refinanced. Under Civil Code §8424, the owner may obtain a release of the lien by recording a lien release bond in the amount of:
Explanation
§8424(b) fixes the bond at 125 percent of the claim of lien — or 125 percent of the amount the claim allocates to the property being released — and requires it to be executed by an admitted surety insurer. On recordation the real property is released from the lien and from any action to enforce it, and the 25 percent margin is there to cover the interest and costs the claimant may recover. The party who records the bond must give the claimant notice with a copy of it, and the claimant then has six months from that notice to sue on the bond, which is a different clock from the 90 days §8460 allows for suing on the lien itself. So (d) is 25 points short, (b) invents a discount for a disputed lien, and (a) is wrong twice over: cash is not required and a surety bond is exactly what the section calls for.
Law Reference: Civil Code §8424(b)-(d); §8460(a)This topic, taught in full in the CSLB Law & Business guide. CSLB Law & Business — Complete Study Guide (2026) — PDF + EPUB, $24.99 · 14-day refund →
Practice all 1632 questions free — no signup required.
Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →
Related questions on this topic
- A licensed contractor organized as a joint venture under §7029, with no employees, has filed an Exemption from Workers' Compensation with the CSLB. The joint venture then hires an employee. Under Bus. & Prof. Code §7125 and §7125.4, what must it do?
- A material supplier delivers $40,000 of lumber to a private construction project on July 1. To fully preserve mechanics' lien, stop payment notice, AND payment bond claim rights, the supplier must serve a preliminary notice under Civil Code §8200 on the owner, direct contractor, and construction lender no later than:
- On a PUBLIC works project, a subcontractor with unpaid invoices serves a 'stop payment notice' on the public entity under Civil Code §9358 (formerly known as a 'stop notice'). The effect is to:
- Claims against a contractor's $25,000 license bond total far more than $25,000: a residential homeowner claims $40,000, an unpaid framer claims $8,000 in wages, and a commercial property owner claims $30,000. Under Bus. & Prof. Code §7071.11, how is the bond distributed?
- A subcontractor's commercial general liability (CGL) policy provides 'additional insured' status to the prime contractor for the sub's negligent work. If a third party is injured and sues both the sub and prime, under California law:
- An unpaid framing subcontractor furnished labor and materials to a private remodel. Who is entitled to record a mechanics lien?
Last reviewed: · editorial process