合同与履行第 741 / 1605 题

A contractor completes 40% of a $20,000 job. Under §7159, the maximum he may have collected by that point (excluding a lawful down payment) is generally:

a.Nothing until 100% complete
b.$15,000
c.About the value of the work performed and materials delivered, roughly $8,000
d.The full $20,000

解析

Progress payments may not exceed the value of work performed and materials delivered. At 40% completion, collections should track roughly that value, about $8,000, plus any lawful down payment.

法律依据: B&P §7159(d)

免费刷完整 1605 道题库 — 无需注册。

同考点相关题目

最近核对: · 审核流程

Sen Lin, PrepPass 创始人 · 依据官方资料核对 California CSLB Contractor License Law & Business Exam · 我们如何核对
审核人 Abraham Chen Licensed California General Contractor (CSLB License #1101856 核实)
反馈