合同与履行第 742 / 1605 题

The down payment and progress payment limits in §7159 are designed primarily to:

a.Protect the homeowner from paying for work not yet done
b.Increase the contractor's cash flow
c.Guarantee the contractor's profit
d.Reduce the CSLB's workload

解析

The payment restrictions in B&P §7159 protect homeowners by ensuring they do not pay substantially ahead of the work actually completed, reducing loss if a contractor abandons the job.

法律依据: B&P §7159