合同与履行第 753 / 1605 题

The $500 threshold that triggers a written home improvement contract is measured by:

a.The aggregate contract price, including both labor and materials
b.Labor cost only
c.The permit fee
d.Materials cost only

解析

B&P §7159 uses the aggregate contract price, combining labor and materials, to determine whether the $500 threshold requiring a written contract is exceeded.

法律依据: B&P §7159

免费刷完整 1605 道题库 — 无需注册。

同考点相关题目

最近核对: · 审核流程

Sen Lin, PrepPass 创始人 · 依据官方资料核对 California CSLB Contractor License Law & Business Exam · 我们如何核对
审核人 Abraham Chen Licensed California General Contractor (CSLB License #1101856 核实)
反馈