Which is TRUE about a home improvement contract that omits the required Mechanics Lien Warning?
a.The omission violates §7159 and can subject the contractor to discipline
b.It is unaffected; the warning is optional
c.The warning is only needed for new construction
d.The warning applies only to commercial jobs
解析
The Mechanics Lien Warning is a mandatory element under B&P §7159; omitting it violates the statute and is grounds for disciplinary action.
法律依据: B&P §7159免费刷完整 1605 道题库 — 无需注册。
同考点相关题目
- What must a home improvement contract state about extra or unforeseen work discovered mid-project?
- The $500 threshold that triggers a written home improvement contract is measured by:
- A home improvement salesperson may lawfully:
- The five-business-day cancellation right is extended to which category of home improvement buyers?
- A homeowner insists on paying the full $30,000 up front to 'lock in the price.' The contractor should know that accepting this:
- Which is a required feature of the progress payment schedule in a home improvement contract?