A contractor uses one contract to cover both a $400 gutter cleaning and a $9,000 addition, calling the whole thing a 'service call.' The addition portion:
a.Requires a full home improvement contract complying with §7159
b.Can avoid §7159 by bundling
c.Needs only a verbal quote
d.Is exempt as maintenance
解析
A $9,000 room addition is a home improvement well over $500; it cannot escape §7159's requirements by being bundled with a minor service task.
法律依据: B&P §7159免费刷完整 1605 道题库 — 无需注册。
同考点相关题目
- A homeowner signs a contract that does not include the contractor's license number. This omission:
- The primary purpose of requiring detailed written home improvement contracts is to:
- Which is a required condition for a service and repair contract under §7159.10?
- When a contract funds are placed in an approved joint control, the joint control company's role is to:
- A home improvement contract must be dated. The date is important primarily because it:
- Abandoning a home improvement project without legal excuse after starting is: