When a contract funds are placed in an approved joint control, the joint control company's role is to:
a.Disburse funds to the contractor as work is verified complete
b.Perform the construction work
c.Sell the property
d.Issue the building permit
解析
A joint control (funding control) company holds the project funds and releases them to the contractor only as work is verified, which is why standard payment limits may be relaxed when one is used.
法律依据: B&P §7159免费刷完整 1605 道题库 — 无需注册。
同考点相关题目
- The primary purpose of requiring detailed written home improvement contracts is to:
- Which is a required condition for a service and repair contract under §7159.10?
- A contractor uses one contract to cover both a $400 gutter cleaning and a $9,000 addition, calling the whole thing a 'service call.' The addition portion:
- A home improvement contract must be dated. The date is important primarily because it:
- Abandoning a home improvement project without legal excuse after starting is:
- A contractor's home improvement contract lists the total price but no breakdown of the payment schedule. Under §7159, this is: