合同与履行第 773 / 1605 题
A contractor's home improvement contract lists the total price but no breakdown of the payment schedule. Under §7159, this is:
a.Non-compliant, because a schedule of progress payments is required
b.Fully compliant
c.Only an issue if the buyer is a senior
d.Acceptable for jobs under $10,000
解析
B&P §7159 requires a schedule of progress payments describing each phase and its dollar amount; a contract that lists only a total price fails this requirement.
法律依据: B&P §7159免费刷完整 1605 道题库 — 无需注册。
同考点相关题目
- When a contract funds are placed in an approved joint control, the joint control company's role is to:
- A home improvement contract must be dated. The date is important primarily because it:
- Abandoning a home improvement project without legal excuse after starting is:
- A homeowner requests a $500 furnace repair by phone. The contractor may present a service and repair contract that must include:
- A contractor prints two identical cancellation notices and attaches them to the contract. This satisfies the requirement that the buyer receive:
- On a $3,000 fence job with no joint control, the maximum lawful down payment is: