合同与履行第 774 / 1605 题

A homeowner requests a $500 furnace repair by phone. The contractor may present a service and repair contract that must include:

a.Required notices including a description of the work and consumer-protection language
b.A 10-year exclusive service clause
c.A demand for full prepayment
d.The homeowner's financial statements

解析

Even the streamlined service and repair contract under §7159.10 must include specified content, such as a description of the requested work and the mandated consumer notices.

法律依据: B&P §7159.10