合同与履行第 776 / 1605 题
On a $3,000 fence job with no joint control, the maximum lawful down payment is:
a.$1,500
b.$600
c.$1,000
d.$300
解析
Ten percent of $3,000 is $300, which is less than the $1,000 cap. Because the limit is the lesser of the two, the maximum down payment is $300.
法律依据: B&P §7159(d)免费刷完整 1605 道题库 — 无需注册。
同考点相关题目
- A contractor's home improvement contract lists the total price but no breakdown of the payment schedule. Under §7159, this is:
- A homeowner requests a $500 furnace repair by phone. The contractor may present a service and repair contract that must include:
- A contractor prints two identical cancellation notices and attaches them to the contract. This satisfies the requirement that the buyer receive:
- The requirement that a home improvement contract be signed before work begins protects the buyer by:
- Which best distinguishes when a contractor should use a service and repair contract versus a home improvement contract?
- A home improvement contract's list of documents incorporated by reference (such as plans and specifications) must be: