A contractor's estimate is not the same as a contract because the required home improvement contract must, unlike a mere estimate:

a.Contain the mandatory notices, payment schedule, dates, and signatures required by §7159
b.Be printed in color
c.Include the contractor's tax return
d.Be notarized by a bank

解析

A binding §7159 home improvement contract must contain specific mandatory elements, notices, dates, a payment schedule, and signatures, which a simple price estimate lacks.

法律依据: B&P §7159