Tooled or sawn control (contraction) joints are placed in a concrete slab-on-grade PRIMARILY to:
a.Increase the load-carrying capacity of the slab
b.Provide a decorative surface pattern
c.Allow the slab to expand upward during hot weather
d.Control where shrinkage cracking occurs by creating planned weak planes
Explanation
Control joints create planned weakened planes so drying-shrinkage cracks form neatly along the joint rather than randomly across the slab. They do not add structural capacity, are not primarily decorative, and are for shrinkage control rather than upward expansion.
Law Reference: 2025 CA Building Code, Chapter 19 (Concrete)Practice all 700 questions free — no signup required.
Related questions on this topic
- For typical residential foundations in a moderate weathering region, what is a common MINIMUM specified 28-day compressive strength for the concrete?
- A continuous foundation footing is 18 inches wide, 10 inches deep, and 90 feet long. Approximately how many cubic yards of concrete does it contain?
- When placing concrete in cold weather, the MOST important protective measure is to:
- A concrete foundation wall is 8 ft tall, 40 ft long, and 8 inches thick. Approximately how many cubic yards of concrete are needed (no waste allowance)?
- Rebar chairs and bar supports are used during concrete placement PRIMARILY to:
- When selecting the maximum size of coarse aggregate for reinforced concrete, a common limit is that the aggregate should NOT exceed:
Last reviewed: · editorial process
PrepPass Editorial Team · Verified against California CSLB General Building (B) Trade Examination · How we review