Framing & StructuralQuestion 384 of 700

In a wood-framed shear wall resisting seismic loads, what is the PRIMARY function of a hold-down device installed at the wall ends?

a.To level the top plate during framing
b.To provide a nailing surface for siding
c.To resist overturning uplift and anchor the end post to the foundation
d.To act as a vapor barrier at the wall base

Explanation

A hold-down ties the shear wall's end post (chord) to the foundation to resist the uplift produced when lateral forces try to overturn the wall. It does not level plates, provide siding nailing, or act as a vapor barrier; those are unrelated framing or moisture functions.

Law Reference: 2025 CA Residential Code §R602.10