The written specifications call for Type X gypsum board, but the plan detail simply notes '5/8 in drywall.' In the contract documents, how are such conflicts typically resolved?

a.The specifications generally govern over the drawings for material quality, but the contractor should seek written clarification
b.The drawings always override the specifications
c.The lowest-cost interpretation automatically applies
d.Whatever the crew installs first becomes the standard

Explanation

When drawings and specifications conflict, the specifications typically govern for materials and quality of work, while drawings govern for dimensions and location; however, the BEST practice is to request a written clarification or RFI so intent is documented. Options b and c are false generalizations, and option d ignores the contract hierarchy and invites disputes and rework.

Practice all 700 questions free — no signup required.

Related questions on this topic

Last reviewed: · editorial process

PrepPass Editorial Team · Verified against California CSLB General Building (B) Trade Examination · How we review
Report