A large earthwork site keeps tracking mud onto the public street. Which best management practice (BMP) BEST addresses this under the site's storm water plan?
a.Sweep the mud into the storm drain each evening
b.Wash the street with a hose into the gutter
c.Ignore it because rain will wash it away
d.Install a stabilized construction entrance and clean tracked sediment from the street
Explanation
A stabilized construction entrance of crushed rock knocks mud off tires before vehicles reach pavement, and any tracked sediment should be swept up and disposed of properly, not washed into drains. Options a and b send sediment straight into the storm drain system, a violation. Option c allows pollution to reach waterways. Preventing and cleaning track-out protects water quality and keeps the site compliant.
Practice all 700 questions free — no signup required.
Related questions on this topic
- On a 55 mph roadway you must close a lane and shift traffic 12 feet. Using the merging taper formula L equals W times S for speeds of 45 mph and above (L in feet, W in feet, S in mph), what is the MINIMUM taper length?
- A flagger controls traffic at a work zone on a city street. Which practice BEST follows California MUTCD flagging guidance?
- A temporary traffic control zone is being set up. What is the PRIMARY purpose of the advance warning area with signs placed before the work?
- Concrete trucks need a place to rinse out their chutes on site. What is the BEST practice to protect the environment?
- Drums of fuel and solvents are stored on a jobsite. What is the BEST practice to prevent spills from reaching soil or storm drains?
- Before demolishing interior finishes in a commercial building from the 1970s, what is the BEST first step regarding possible asbestos?
Last reviewed: · editorial process
PrepPass Editorial Team · Verified against California CSLB General Building (B) Trade Examination · How we review