Before a mobile crane makes a lift on a jobsite, which combination of practices BEST supports a safe lift?
a.Guess the load weight and lift quickly
b.Skip the load chart if the operator is experienced
c.Set outriggers on firm, level ground with proper pads and stay within the crane's rated load chart
d.Extend the boom fully to keep loads far from the crane
Explanation
A safe lift requires the crane set on firm, level ground with outriggers fully deployed on adequate pads, and the load kept within the capacity shown on the rated load chart for that configuration. Option a and b abandon the engineering controls that prevent overloading and tip-over. Option d increases the load radius, which sharply reduces capacity and can cause tipping. Ground support, outriggers, and the load chart together keep the lift within safe limits.
Practice all 700 questions free — no signup required.
Related questions on this topic
- Workers will sand and torch-cut steel coated with old lead-based paint. Under Cal/OSHA lead rules, what is the BEST early step to protect them?
- Under Cal/OSHA, what safety document must every California construction employer establish and maintain in writing?
- A worker operates from the platform of an articulating boom lift. What is the BEST fall-protection practice for that worker?
- A complete personal fall arrest system (PFAS) is often remembered by the letters A-B-C-D. Which set of components does this represent?
- An employer proposes using a body belt (a single strap around the waist) as the attachment for a worker's fall ARREST system. Under Cal/OSHA, what is the BEST assessment?
- CALCULATION: A worker's PFAS allows a maximum free fall of 6 ft and, once the shock-absorbing lanyard deploys, up to 3.5 ft of deceleration distance. Adding a 5 ft worker height plus a 2 ft safety margin, what is the MINIMUM vertical clearance needed below the anchorage-level walking surface to avoid hitting the lower level?
Last reviewed: · editorial process
PrepPass Editorial Team · Verified against California CSLB General Building (B) Trade Examination · How we review