Match each work item to its CSI MasterFormat division: (i) built-up roofing and wall insulation, (ii) interior painting and ceramic tile, (iii) exterior aluminum windows.

a.(i) 09, (ii) 07, (iii) 05
b.(i) 07, (ii) 09, (iii) 08
c.(i) 08, (ii) 07, (iii) 09
d.(i) 05, (ii) 08, (iii) 07

Explanation

Correct: roofing, waterproofing, and insulation are Division 07 (Thermal & Moisture Protection); painting and tile are Division 09 (Finishes); windows and doors are Division 08 (Openings). The other options scramble these assignments.