Planning & EstimatingQuestion 631 of 700
Match each work item to its CSI MasterFormat division: (i) built-up roofing and wall insulation, (ii) interior painting and ceramic tile, (iii) exterior aluminum windows.
a.(i) 09, (ii) 07, (iii) 05
b.(i) 07, (ii) 09, (iii) 08
c.(i) 08, (ii) 07, (iii) 09
d.(i) 05, (ii) 08, (iii) 07
Explanation
Correct: roofing, waterproofing, and insulation are Division 07 (Thermal & Moisture Protection); painting and tile are Division 09 (Finishes); windows and doors are Division 08 (Openings). The other options scramble these assignments.
Practice all 700 questions free — no signup required.
Related questions on this topic
- Under CSI MasterFormat, cast-in-place structural concrete work is specified under which division?
- Under CSI MasterFormat, concrete masonry unit (CMU) and brick work fall under which division?
- Structural steel framing and steel joists are specified under which CSI MasterFormat division?
- When contract documents conflict and there is no special precedence clause, which GENERAL rule do most construction contracts apply?
- On a drawing at 1/4 inch = 1 foot-0 inches, a wall measures 3 inches long on the paper. What is the actual length of that wall?
- On a civil drawing using an engineer's scale of 1 inch = 20 feet, a property line measures 4.5 inches on the paper. What is its actual length, and how does an engineer's scale differ from an architect's scale?
Last reviewed: · editorial process
PrepPass Editorial Team · Verified against California CSLB General Building (B) Trade Examination · How we review