Core TradesQuestion 70 of 700
A concrete supplier delivers a load with a measured slump much higher than ordered. Before rejecting or accepting, the BEST assumption about the likely cause and its effect is:
a.High slump means higher strength, so accept it
b.Slump does not affect the finished concrete
c.The load is too stiff and needs vibration
d.Water was likely added on site, which raises the water-cement ratio and can reduce strength and durability
Explanation
An unexpectedly high slump usually means water was added, increasing the water-cement ratio and lowering strength and durability. High slump does not indicate higher strength; slump affects workability and quality; a high slump is fluid, not stiff. Field-added water beyond the design must be evaluated before acceptance.
Law Reference: 2025 CA Building Code, Chapter 19 (Concrete)Practice all 700 questions free — no signup required.
Related questions on this topic
- CALCULATION: A slab-on-grade measures 30 ft by 24 ft and is 5 inches thick. How many cubic yards of concrete are required, before adding waste?
- CALCULATION: A continuous footing is 60 feet long, 20 inches wide, and 12 inches deep. Approximately how many cubic yards of concrete does it require?
- CALCULATION: A rectangular column is 18 in by 18 in in cross-section and 10 feet tall. Ignoring reinforcement, how many cubic yards of concrete does it contain?
- During hot-weather concreting at 95 degrees F with dry wind, the MOST important immediate practice to prevent surface defects is to:
- A driveway slab cracks in a fairly straight line directly over a buried utility trench that was backfilled. The MOST likely cause is:
- Control joints (contraction joints) are tooled or saw-cut into a slab primarily to:
Last reviewed: · editorial process