For a construction stormwater permit (SWPPP), who is generally responsible for ensuring the plan is implemented and its control measures are inspected and maintained on the site?
a.Only the state agency that issued the permit
b.The permit holder/legally responsible person (such as the owner or their contractor), who must implement, inspect, and maintain the BMPs
c.Only the concrete supplier delivering to the site
d.No one until a violation notice is received
Explanation
Correct: the discharger who holds the permit, the legally responsible party such as the owner or their designated contractor, is responsible for implementing the SWPPP and for inspecting and maintaining the control measures (BMPs) throughout construction. The issuing agency oversees but does not run daily site controls. A material supplier is not responsible for site-wide stormwater compliance. Waiting for a violation notice is noncompliant; the duty is ongoing.
Practice all 700 questions free — no signup required.
Related questions on this topic
- How should flammable liquids like gasoline and solvents be stored on a construction site?
- On a 40 mph roadway you must shift traffic laterally by 10 feet with a merging taper. For speeds of 40 mph or less the taper length formula is L = W x S squared / 60 (L in feet, W = offset in feet, S = speed in mph). What is the MINIMUM taper length?
- In a taper on a 45 mph roadway, a common rule of thumb for the maximum spacing between channelizing devices (cones) in the taper is that the spacing in feet should be about equal to the speed in mph. Roughly what maximum cone spacing does that give?
- A temporary traffic control (TTC) zone is typically divided into four areas. Which sequence correctly lists them in the order a driver encounters them?
- A flagger controls traffic in a work zone. Which combination BEST matches California MUTCD flagging requirements?
- A construction site's storm water plan (SWPPP) requires controlling sediment at the point where runoff leaves the site through a street drain. Which best management practice DIRECTLY protects that storm drain inlet?