Core TradesQuestion 93 of 700

CALCULATION: A vertical drainage stack must accommodate horizontal branch offsets. A trap arm for a 2-inch fixture drain is allowed a maximum developed length. If the code table permits 8 feet for a 2-inch trap arm, and the layout requires 11 feet to the vent, the installer should:

a.Ignore the limit; length does not matter
b.Relocate the vent or add a vent so the trap arm is within 8 feet
c.Increase the slope to 1 inch per foot
d.Use a smaller 1-1/2 inch trap arm

Explanation

If the required trap-arm length exceeds the code maximum for that size, the fix is to bring the vent closer (relocate or add a vent) so the arm is within the allowed developed length, preventing self-siphonage. Ignoring the limit risks trap-seal loss; over-steepening or downsizing does not resolve the length limit.

Law Reference: 2025 CA Plumbing Code

Practice all 700 questions free — no signup required.

Related questions on this topic

Last reviewed: · editorial process

PrepPass Editorial Team · Verified against California CSLB General Building (B) Trade Examination · How we review
Report