A documented, agreed adjustment to the contracted scope of work and price is called what?
a.A request for information
b.A submittal
c.A material takeoff
d.A change order
Explanation
A change order is the written, mutually agreed document that modifies the contract's scope and price. An RFI asks a question, a submittal proposes products for approval, and a takeoff counts materials.
Practice all 521 questions free — no signup required.
Related questions on this topic
- What does a plot (site) plan primarily show?
- What does a detail drawing on a set of plans typically show?
- When the drawings or specifications are unclear, what document does the contractor typically submit to the designer for clarification?
- Who typically performs the code-compliance inspections on a permitted electrical project?
- A dwelling's standard-method net calculated load is 28,600 VA on a 240 V service. What is the smallest standard service size that will carry it?
- Using Table 250.66, for copper service-entrance conductors of 3/0 AWG, what is the minimum size copper grounding electrode conductor?
Last reviewed: · editorial process
PrepPass Editorial Team · Verified against California CSLB C-10 Electrical Trade Examination · How we review