Which sequence correctly describes the basic lockout/tagout procedure before servicing electrical equipment?

a.Notify affected employees, shut down, isolate/disconnect the energy source, apply locks and tags, release stored energy, then verify zero energy
b.Apply locks first, then shut down, verify, and notify workers
c.Verify zero energy, apply tags, shut down, then isolate
d.Shut down, energize a test circuit, remove guards, then lock

Explanation

The correct order is to notify, shut down, isolate, lock and tag, release stored energy, and finally verify zero energy. You cannot lock before shutting down, and verification must come at the end—not before isolation. Removing guards on a live test circuit is unsafe.

Law Reference: Cal/OSHA Title 8 §3314