Load & DesignQuestion 8 of 110
After a Manual J load is calculated, which ACCA procedure is used to select the specific equipment model?
a.Manual D
b.Manual T
c.Manual S
d.Manual RS
Explanation
Manual S matches equipment to the Manual J loads using manufacturer expanded performance data at local design conditions. It ensures the unit meets both sensible and latent loads without gross oversizing. Oversized equipment short-cycles and dehumidifies poorly.
Practice all 110 questions free — no signup required.
Related questions on this topic
- The sensible heat formula uses which constant when air volume is in CFM and temperature difference is in degrees F?
- Using the sensible heat formula, how much sensible heat is removed when 1,200 CFM of air is cooled through a 20 degree F temperature drop?
- What does ACCA Manual D provide guidance for?
- Oversizing a residential air conditioner most commonly leads to which problem?
- Which factor increases a building's cooling load the most on a hot afternoon?
- In California, plans for new HVAC systems typically must demonstrate compliance with which energy standard?
Last reviewed: · editorial process
PrepPass Editorial Team · Verified against California CSLB C-20 Warm-Air HVAC Trade Exam · How we review