Planning & EstimatingQuestion 286 of 360
On the plans a valve symbol drawn as two triangles meeting point-to-point (a bowtie) most commonly represents which device?
a.A pipe hanger
b.A cleanout
c.A gate or general shutoff valve
d.A floor sink
Explanation
The bowtie of two triangles meeting at their points is the standard schematic symbol for a valve, commonly a gate or general shutoff valve, with added marks distinguishing specific types. Reading valve symbols lets you count and locate shutoffs during takeoff. The plan's legend defines which valve type each variation means.
Practice all 360 questions free — no signup required.
Related questions on this topic
- When you coordinate plumbing rough-in with the framing crew, why is it important to review the structural drawings before drilling floor joists?
- You are planning the DWV rough-in test. Under the CPC, a water test of the drainage and vent system is applied so that no section is tested with less than how much head of water?
- In estimating pipe for a run, why do experienced estimators add a waste/scrap allowance to the measured length?
- A restaurant plan calls for eight identical mop-sink rough-ins. Each rough-in needs 1 P-trap, 1 trap adapter, and 2 drop-ear elbows. How many drop-ear elbows go on the takeoff?
- While laying out the building drain you reach a 90° change of direction. Under the CPC, what feature is generally required at such a change of direction on the horizontal drain?
- What is the main purpose of a plumbing fixture schedule on a set of plans?