Under the CPC, what is the general purpose of requiring a permit and inspections for plumbing work?
a.To increase the contractor's profit
b.To choose the fixture brand
c.To schedule the painters
d.To ensure the installation is reviewed and inspected for conformance with the code before it is placed in service
Explanation
CPC 103.0 provides for permits and inspections so that regulated plumbing work is reviewed and verified to conform with the code before use. This protects public health and safety by confirming the system is installed correctly. Planning for required permits and inspection hold points is part of every compliant job.
Law Reference: CPC 103.0Practice all 360 questions free — no signup required.
Related questions on this topic
- When must a plumbing permit generally be obtained relative to starting the work?
- A single-line water piping diagram on the plans is best described as what?
- When planning the drainage layout, why must roof and storm drainage generally be kept separate from the sanitary drainage system?
- A bid schedule shows the plumbing rough-in must be complete before the concrete slab is poured. What does this tell you about coordination?
- You are counting fixtures for a two-bathroom house: each bathroom has 1 water closet, 1 lavatory, and 1 shower, and the kitchen has 1 sink. How many fixtures go on the rough-in count?
- During planning, what is the main reason to record the invert elevation of the sewer point of connection before designing the underground drainage?
Last reviewed: · editorial process
PrepPass Editorial Team · Verified against California CSLB C-36 Plumbing Trade Examination · How we review