Before a plumbing contractor begins excavating for a new sewer lateral, California law requires a step to avoid striking buried utilities. What must the contractor do?

a.Contact the regional one-call center (DigAlert/USA North, dial 811) and wait for utilities to be marked
b.Dig quickly at night when there is less traffic
c.Rely on the homeowner's memory of where lines run
d.Only worry about gas lines, not water or electric

Explanation

California Government Code §4216 (the 'Dig Alert' law) requires an excavator to notify the regional notification center (call 811) at least two working days before digging so utility operators can mark their underground facilities. Striking a gas, electric, or fiber line can be deadly and costly. Hand-digging (potholing) is required near marked lines to expose them safely.

Law Reference: California Government Code §4216

Practice all 360 questions free — no signup required.

Related questions on this topic

Last reviewed: · editorial process

PrepPass Editorial Team · Verified against California CSLB C-36 Plumbing Trade Examination · How we review
Report