Business FinancesQuestion 334 of 1632

A schedule of values that allocates more value to early line items than the work actually justifies is sometimes called "front-loading." From the owner's perspective, the risk of front-loading is that:

a.The job will be reported as ahead of schedule
b.The contractor is overpaid relative to work done
c.The owner will pay less retention than the debt
d.Overhead costs will be left out of the price

Explanation

Front-loading shifts contract value into early line items so the contractor draws more cash than the completed work justifies, and the owner is left holding too little of the price against the work that remains - exactly the security retention is supposed to preserve. Option (a) names a real side effect and mistakes it for the risk: a front-loaded schedule of values does make the job report as further along than it is, because percent complete is computed from billed value, but the harm is the money, not the report. Retention is a percentage of each payment and does not fall because the line items were reshuffled. And overhead sits inside the line items either way.

This topic, taught in full in the CSLB Law & Business guide. CSLB Law & Business — Complete Study Guide (2026) — PDF + EPUB, $24.99 · 14-day refund →

Practice all 1632 questions free — no signup required.

Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →

Related questions on this topic

Last reviewed: · editorial process

PrepPass team · Verified against California CSLB Contractor License Law & Business Exam · How we review
Reviewed by Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — verify)
Report