Business FinancesQuestion 334 of 690
A schedule of values that allocates more value to early line items than the work actually justifies is sometimes called "front-loading." From the owner's perspective, the risk of front-loading is that:
a.The contractor will finish the job too quickly
b.The contractor may be overpaid early relative to work completed, weakening the owner's security
c.The owner will pay less retention than required
d.Overhead costs will be eliminated
Explanation
Front-loading shifts contract value to early activities so the contractor collects more cash up front than the completed work warrants. This leaves the owner under-secured if the contractor later fails to finish.
Practice all 690 questions free — no signup required.
Related questions on this topic
- A contractor's progress payment application bills $80,000 of completed work. The owner withholds 10% retention. How much cash will the contractor actually receive on this payment?
- Which document collects an independent contractor's name, address, and taxpayer identification number so the payer can later issue a 1099-NEC?
- A contractor's overhead is the same each month whether it completes 2 jobs or 8 jobs. Therefore, the per-job share of overhead is LOWEST when the contractor:
- A contractor reviews three completed jobs and finds Job A earned $12,000 profit on $100,000 revenue, Job B earned $9,000 on $90,000, and Job C earned $4,000 on $80,000. Which job had the HIGHEST profit margin?
- A contractor that fails to make required quarterly estimated tax payments to the IRS during the year is most likely to face:
- A contractor's fixed overhead is $9,000 per month and variable costs are 75% of revenue. If the contractor produces $30,000 of revenue in a month, what is the net result for that month?
Last reviewed: · editorial process
PrepPass Editorial Team · Verified against California CSLB Contractor License Law & Business Exam · How we review