A schedule of values that allocates more value to early line items than the work actually justifies is sometimes called "front-loading." From the owner's perspective, the risk of front-loading is that:
Explanation
Front-loading shifts contract value into early line items so the contractor draws more cash than the completed work justifies, and the owner is left holding too little of the price against the work that remains - exactly the security retention is supposed to preserve. Option (a) names a real side effect and mistakes it for the risk: a front-loaded schedule of values does make the job report as further along than it is, because percent complete is computed from billed value, but the harm is the money, not the report. Retention is a percentage of each payment and does not fall because the line items were reshuffled. And overhead sits inside the line items either way.
This topic, taught in full in the CSLB Law & Business guide. CSLB Law & Business — Complete Study Guide (2026) — PDF + EPUB, $24.99 · 14-day refund →
Practice all 1632 questions free — no signup required.
Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →
Related questions on this topic
- A contractor's progress payment application bills $80,000 of completed work. The owner withholds 5% retention. How much cash will the contractor actually receive on this payment?
- Which document collects an independent contractor's name, address, and taxpayer identification number so the payer can later issue a 1099-NEC?
- A contractor's overhead is the same each month whether it completes 2 jobs or 8 jobs. Therefore, the per-job share of overhead is LOWEST when the contractor:
- A contractor reviews three completed jobs and finds Job A earned $12,000 profit on $100,000 revenue, Job B earned $9,000 on $90,000, and Job C earned $4,000 on $80,000. Which job had the HIGHEST profit margin?
- A contractor that fails to make required quarterly estimated tax payments to the IRS during the year is most likely to face:
- A contractor's fixed overhead is $9,000 per month and variable costs are 75% of revenue. If the contractor produces $30,000 of revenue in a month, what is the net result for that month?
Last reviewed: · editorial process