Business FinancesQuestion 336 of 1632

A contractor that fails to make required quarterly estimated tax payments to the IRS during the year is most likely to face:

a.Automatic suspension of the CSLB licence
b.A reduction in the contractor's bonding limits
c.A requirement to switch to accrual accounting
d.An underpayment penalty on the annual return

Explanation

IRC §6654 charges an addition to tax when too little was paid in through estimated instalments during the year, and the charge is computed quarter by quarter on the shortfall, so paying in full with the April return does not cure it. Licence status is a CSLB matter and does not turn on federal tax timing. Bonding limits are the surety's own credit decision. And the method of accounting is chosen under IRC §446 and changed only with IRS consent, never as a penalty.

Law Reference: IRC §6654

This topic, taught in full in the CSLB Law & Business guide. CSLB Law & Business — Complete Study Guide (2026) — PDF + EPUB, $24.99 · 14-day refund →

Practice all 1632 questions free — no signup required.

Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →

Related questions on this topic

Last reviewed: · editorial process

PrepPass team · Verified against California CSLB Contractor License Law & Business Exam · How we review
Reviewed by Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — verify)
Report