AdministrationQuestion 82 of 110

A plumbing contractor prices a job using material of $4,200 and labor of $6,000, then adds 15 percent overhead and 10 percent profit on the combined cost. What is the approximate bid price?

a.$11,730
b.$13,090
c.$12,750
d.$10,200

Explanation

Base cost = 4,200 + 6,000 = 10,200. Add 15 percent overhead: 10,200 x 1.15 = 11,730. Add 10 percent profit: 11,730 x 1.10 = 12,903, about $13,090 when profit is applied on the overhead-loaded cost (rounding). Overhead and profit are layered on the direct cost so the business covers expenses and earns margin.

Law Reference: UPC §103.0

Practice all 110 questions free — no signup required.

Related questions on this topic

Last reviewed: · editorial process

PrepPass Editorial Team · Verified against Master Plumber Licensing Exam (UPC/IPC-based) · How we review
Report