Origination ActivitiesQuestion 261 of 400
A borrower must receive the Closing Disclosure at least how many business days before consummation of the loan?
a.One business day
b.Two business days
c.Three business days
d.Seven business days
Explanation
Under TRID, the creditor must ensure the borrower receives the Closing Disclosure at least three business days before consummation. Certain changes (like an APR increase beyond tolerance) can trigger a new three-day waiting period. The seven-day rule applies to the Loan Estimate before consummation.
Law Reference: TILA-RESPA Integrated Disclosure (TRID)Practice all 400 questions free — no signup required.
Related questions on this topic
- An appraisal report notes the subject property's highest and best use differs from its current use. Why does 'highest and best use' matter in valuation?
- In qualifying an applicant end-to-end, a lender evaluates the 'four Cs.' Which set correctly lists them?
- A processor orders a verification of employment (VOE) but the borrower started a new job last week. What additional step is most appropriate?
- During underwriting, an appraiser identifies functional obsolescence in the subject home. What does functional obsolescence refer to?
- A borrower with strong income but only 90 days of seasoning on a large deposit asks why 'reserves' matter. What are reserves in underwriting?
- A settlement agent prepares to record the deed and mortgage after funding. Recording these documents primarily serves to:
Last reviewed: · editorial process
PrepPass Editorial Team · Verified against NMLS SAFE Mortgage Loan Originator National Test · How we review