Common HazardsQuestion 26 of 100

Where should excavated soil (spoil pile) be placed relative to the edge of a trench?

a.Directly on the trench edge
b.At least 2 feet back from the edge
c.It does not matter
d.Inside the trench

Explanation

Spoil piles and other materials must be kept at least 2 feet back from the edge of an excavation. This reduces the load on the trench walls and prevents materials from rolling back in. Keeping the edge clear also gives workers a safe exit path.