Common HazardsQuestion 41 of 100

Which is the correct order of the hierarchy of controls from most to least effective?

a.Elimination, substitution, engineering controls, administrative controls, PPE
b.PPE, administrative, engineering, substitution, elimination
c.Administrative, PPE, elimination, engineering, substitution
d.Substitution, PPE, elimination, engineering, administrative

Explanation

The correct hierarchy from most to least effective is elimination, substitution, engineering controls, administrative controls, and PPE. Higher-level controls are more reliable because they do not depend on worker behavior. PPE is the last line of defense.

Practice all 100 questions free — no signup required.

Related questions on this topic

Last reviewed: · editorial process

PrepPass Editorial Team · Verified against OSHA 30-Hour Construction Safety · How we review